Mivan technology / Formwork | Introduction



What is Mivan technology

Introduction
-It was developed by MIVAN Company Ltd. from Malaysia in the 1990s for constructing mass housing projects in developing countries. 
-MIVAN Company Ltd. began manufacturing these formworks, hence giving the name “MIVAN Technology”
-MIVAN formwork technology uses aluminium alloy formwork into which concrete is poured into making a mould.
-The system of aluminium forms (MIVAN) has been used widely in the construction of residential units and mass housing projects. It is fast, simple, adaptable and cost – effective. 
-This system is most suitable for Indian condition as a tailor–made aluminium formwork for cast–in–situ fully concrete structure.

Features of Mivan technology

1. Sheet thickness and size of panel 
-The concrete wall panel is 5mm thick. 
2000*600, 2000*300, 1200*300, 850*300 are the standard sizes of panels. 
-Any other required size as per the requirement can be manufactured and delivered to the site. 
-Panels reusable upto 250 times
2. Load carrying capacity 
-It has 7-8 tonnes per square meter capacity. 
-Due to use of aluminium as a material, it is light in weight. 
-It weigh around 18-20kg per square meter. 
3. Striking time 
Vertical formwork - 12hours after concreting or when concrete attends a strength of 2N/mm2 
Horizontal formwork – 36hours after concreting or when concrete attends a strength of 10N/mm2 
4. Cycle Time
-High speed of construction can be achieved by this system that means faster completion of project.
-5 Days per floor.

Fig. Shows Mivan shuttering
Mivan floor cycle (5 days )
The formwork assembling at the site is a quick & easy process. All formwork begins from corners and proceeds from there. 
The system usually follows a 5 day slab cycle: -
Day 1: The first activity consists of erection of vertical reinforcement bars 
Day 2: one side of the vertical formwork for the entire floor or a part of one floor.
Day 3: The second activity involves erection of the second side of the vertical   formwork and formwork for the floor 
Day 4: Fixing reinforcement bars for floor slabs
Day 5: After completion of all checking, Casting of walls and slabs.

Removal of vertical form work panels after 24hours, leaving the props in place for 7 days and floor slab formwork in place for 2.5 days.

Advantages of Mivan technology
-Uniformity in all components of structures. 
-There is no need of block work
-Wall and slabs have smooth surface, which eliminates internal Plastering work
-This technology makes the structures more seismic resistant and durable as well
-Casting of all structural member is done at a single pour of concrete. 
-Scrap value is high. 
-Can be erected using unskilled labours and without the removing of props, deck panel can be removed

Disadvantages of Mivan technology
-Due to casting of all members, any modification is not possible to carry out. 
-Due to presence of shear wall, heat of hydration is high. 
-Initial cost is high 
-Not suitable for small scale projects. 
-Wall and slab may show cracks due to shrinkage