Checklist for Shuttering / Formwork
SHUTTERING: (Material Inspection ,Staging & Erection)
- check Architectural/R.C.C.
Details as per drawings.
- check method statement
approved as per companies standard
- Check for design of
shuttering/shuttering scheme
1. Plywood
Surface:
- Pilled off
- Mould Oil Applied
- Holes/Gaps Sealed
- Cleanliness
- Edges damaged
- Warp age
2. STEEL
-wall form panels
-corner angles
-jacks
-base plates
-clamps & couplers
- channels, clips, pipes
3. Formwork Alignment, formwork level
4. Verticality
5. Form Ties In Position
6. Form Ties Fastened
7. Bracing In Position
8. Rigidity Of Joints Between Panels
9. Timber Members In Good Condition
10. Steel Members Properly Welded/Bolted
11. Member Sizes And Positions According To Design.(Walers, Studs, Plates, wall plates, bolts etc)
12. Scaffolding/Props/Spans
13. Construction/Expansion Joint Details
14. Holes for Electrical Conduits/ Dowels etc.
15. Openings For Services
16. Tolerances in mm
17. Spacing of props
18. Spacing of Spans
19. Check for Readiness of shutter forms for Release to fix reinforcement
20. Has the consultant inspected the formwork before concreting
21. Stripping time/date
Deshuttering points
1. Check whether concrete quality is free from defects after de-shuttering
2. Check condition of various parts of shuttering assembly
3. Are repairs carried out to damaged plates and other components of shuttering assembly
4. Clean ,oil and stack shuttering material for future use