Step 1 Study of the drawings
- we study all the Architect, RCC drawings finishing drawings of the building before starting the building construction work, after study of drawings we next do site preparation work Fig. 1 RCC Drawing
Step 2 Site Preparation Work
- As per the drawing, plot area is marked on the field Construction process of building/House
- The Building construction site needs to do cleaning work before the excavation work is executed.
- The removal of debris, cutting of trees, other unwanted materials removed from the site.
- After Cleaning need to do leveling work of the ground Fig. 2 Site Preparation Work
Step 3 Excavation Work
- As per building foundation drawings, starts excavation of the ground.
- Excavation work is done with the help of excavating machines such as JCB, Poclain,etcDND Construction and manually with the help of labors by Hoe or shovels,etc.
- Excavation work done till hard strata is visible. Fig. 3 Excavation Work
Step 4 PCC (Plain Cement Concrete) work
- We remove all excavated materials from the site and cleaning is done properly.
- Concrete low grades like M10, M12.5, or M15 is used for PCC work. Fig. 4 PCC work
Step 5 Foundation Work
A foundation is a lowermost part of a building structure that transfers all building load to the earth.
Foundation work of activity includes
- Reinforcement work of footings
- Shuttering work of footing
- Concrete Pouring work of footings
Step 6 Backfilling work
- Backfilling is the process of filling the excavated Plinth or trenches after the construction of footing.
- Plinth filling is done to fill the area within the Plinth.
- Soil well compacted before starting the plinth work Fig. 6 Backfilling Work
Step 7 Plinth beam and slab work
- The plinth beam and slab make the structured composite
- A plinth beam is a reinforced concrete beam constructed between the wall and its foundation.
- The plinth beam is provided to prevent the extension or propagation of cracks from the foundation into the wall above when the foundation suffers from the settlement.
- Plinth beams distribute the load of the wall over the foundation evenly. Fig. 7 Plinth Beam & Slab work
Step 8 Column Construction Work
The column is a vertical structural member of the building that carries loads mainly in compression.
construction activity of column as follows
Step 9 Slab Construction work
- Reinforcement work of column
- Shuttering work of column
- Concrete Pouring work of column Fig. 8 Column Work
Step 9 Slab Construction work
A slab is a structural element, made of concrete, that is used to create flat horizontal surfaces such as floors, roof decks, and ceilings.
This is how Residential building Construction activities of step by step going on-site. this step varies as per site conditions, these are the basic sequence of activities
Send your opinions and suggestions to email id:dndconstructioncompany@gmail.com
watch this full video on youtube
https://www.youtube.com/watch?v=Q0m0EQoDmkk
- Reinforcement work of slab
- Shuttering work of slab
- Concrete Pouring work of slab Fig. 9 Slab Construction Work
This is how Residential building Construction activities of step by step going on-site. this step varies as per site conditions, these are the basic sequence of activities
Send your opinions and suggestions to email id:dndconstructioncompany@gmail.com
watch this full video on youtube
https://www.youtube.com/watch?v=Q0m0EQoDmkk









0 Comments